MediumRoads

Coffey Park and Fountaingrove road disaster recovery funding

The council awarded a $4.66 million contract to rebuild the Hopper Avenue corridor after the 2017 fires, funded entirely from the Capital Improvement Fund.

5 mentionsLast discussed Aug 4, 2026
HighRoads

Hoen Avenue Traffic Safety

Speakers described dangerous conditions on Hoen Avenue, including past pedestrian fatalities and speeding. Staff noted crash rates are below the state average and that the city has installed flashing beacons and continues safety improvements, with the Southeast Greenway park planned nearby.

2 mentionsLast discussed Jul 28, 2026
HighRoads

Calistoga Road Pavement Rehabilitation

A $10.6 million contract will repave Calistoga Road from Montecito Boulevard to Highway 12 and add utility improvements — long-awaited relief for a heavily traveled corridor.

4 mentionsLast discussed Jun 2, 2026
LowRoads

Pierson Street rehabilitation

A $1.58 million contract was awarded to repave Pierson Street, funded entirely by capital improvement money — no general fund dollars.

1 mentionLast discussed Apr 21, 2026
HighRoads

Highway 101 overcrossing cost concerns

The council awarded the $37.6 million construction contract to Ghilotti Construction — about 29% over estimate — because rebidding would miss grant deadlines. A bid protest from the losing bidder was heard.

4 mentionsLast discussed Apr 7, 2026
MediumRoads

Golden Gate Transit late-night service cuts

Speakers warned that regional bus service between Sonoma County and San Francisco will largely vanish after 8 p.m. starting April 12, following a $5.5 million county funding cut — leaving night-shift workers stranded.